WHERE WE’RE WORKING

Click through the year buttons below to learn when each Upgrade Downtown
project will be completed.

In 2017, crews replaced water pipes on Hamilton Avenue between Emerson and Webster and on Everett Avenue between Alma and Ramona.  Crews also improved Middlefield Road between Lowell Avenue and Palo Alto Avenue. Work included replacement of curbs and gutters, implementation of transportation improvements, and paving Middlefield Road from Lowell to Forest Avenue. On Middlefield Road between Forest Avenue and Palo Alto Avenue, the Transportation Division changed the lane configuration of the roadway to implement the Middlefield North Traffic Safety Project. The lane changes were approved by City Council for a 1-year pilot project.

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
In 2018, water and/or gas pipes will be replaced on the following streets:
• University Avenue between University Circle and Webster Street
• Hawthorne Avenue between Alma Street and Middlefield Road
• Everett Avenue between Ramona Street and Middlefield Road 
• Lytton Avenue between Waverley and Webster streets
• Hamilton between Waverley and Cowper streets
• Forest Avenue between Alma and Ramona streets
• Homer Avenue between High and Emerson streets
• High Street between Lytton and Hamilton avenues
• Emerson Street between Everett and Hamilton avenues
• Bryant Street between Lytton and Forest avenues
• Cowper Street between Lytton and University avenues and between Hamilton
  and Forrest avenues
• Tasso Street between Lytton and University avenues
• Webster Street between Everett and Lytton avenues
Crews will also begin improving Alma Street between Melville Avenue and Palo Alto Avenue, Lane 33 from Ruthven Avenue to Cowper Street, and Whitman Court from Bryant Street to Waverley Street.

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
In 2019, gas pipes will be replaced on the following streets:
• Hawthorne Avenue between Alma and Bryant streets
• Everett Avenue between Alma and Bryant streets, and between Fulton and Palo Alto avenues
• High Street between Hawthorne and Everett avenues
• Ramona Street between Everett and Lytton avenues
• Kipling Street between Hawthorne and Everett avenues
After pipes are replaced, street improvement work will begin on Hawthorne Avenue between Emerson Street and Middlefield Road, on Everett Avenue between Alma Street and Fulton Avenue, on University Avenue between Alma and Webster streets, and on Downing Lane between Forest and Homer avenues. Parking enhancements, including a new parking structure, will occur between 2018 and 2020.

In 2020, street improvement work will begin on Emerson Street, between Palo Alto Avenue and Forest Avenue, and on Webster Street between Hawthorne and Lytton Avenues. Parking enhancements, including a new parking structure, will occur between 2018 and 2020.

In 2021, street improvement work will begin on the following lanes:
• Lane 30 between Waverley and Kipling streets
• Lane 5 East from High Street to Hamilton Avenue
• Lane 6 East between High and Emerson streets
• Lane 7 East between Forest and Homer avenues
• Lane 7 West between Forest and Homer avenues